Steps to oversee the implementation of projects- buildings 1

Of the budget settlement and the retina:
1 - Verification of the removal of waste and constraints of the site.
2 - Review the zero level of the site to rate levels constant (Alruper) bench mark
3 - Review of the Budget web site.
Planning work:
1 - Review the signing of the project points to determine the nature of the different parts of the project.
2 - Review the project to link levels of contour intervals surrounding streets, as well as services and facilities to those streets.
3 - Review the work of the framework to install it on the axes of the building to be created, taking into account not only remove the frame after pouring foundations and columns of the ground.
4 - Review to install themes on the frame according to the charts.
Excavation work:
1 - Review the rules and sign Almidat and any other acts that require drilling and the adoption of the dimensions of the pits.
2 - to give permission for the drilling contractor.
3 - Receive the excavation work in accordance with the dimensions and elevations contained drawings specifying the thickness of normal concrete.

Foundation work:
Normal concrete:
1 - Review and approve the regular concrete mix design specifications.
2 - give permission to the contractor casting according to the form prepared for this purpose (Form No. 6).
3 - overseeing the casting process and verification of textures - the mechanical shaking - Finish the surface).
4 - check address the concrete according to specifications and for the period specified.
5 - Verification of the isolation of the surface of normal concrete (if any).