Stages and the basic rules - Phase Executive 10

Preparation of change orders:
Shall be in accordance with Article No. (44) of the Public Works contract, which states:
(The engineer to set a limit value, if any, deemed to be added or deducted from the amount mentioned in the tender for any work of plus or more were executed or canceled upon his command, being a calendar of such work in accordance with the rates mentioned in the contract if the opinion of the Engineer as applicable .. If the contract does not contain any rates applicable to over-work or overtime; the employer and the contractor may agree to determine a fair price for it.) and follow the procedural steps are the following:
- Study the business to be added, deleted, or replaced by a comprehensive study and processing of plans and calculation of quantities and costs if they have similar items in the contract.
- Not to scale if those acts similar items in the contract (ie, it updated the terms of) the contractor shall be notified of such work for study and prices for their implementation, and then negotiate with him to get the price prevailing in the region.
- The value of the items and quantities are not implemented (savings) to cover the value of items and additional work (increases) and is a statement of quantity and value of savings and increases (Form No. 9) and determine the percentage of the value of each to the value of the contract.
- Is released, sets the record business, quantity, cost and implementation time if the assignment has been in a period of not allowing the contractor to the implementation of these actions during the term of the contract (Form No. 10).
- Is the lifting of all documents to the authority for approval, and then issue the decision of the baptism of the contractor to the implementation of those actions.

Last Update
11/4/2011 9:40:17 PM