Stages and the basic rules - Phase Executive 13

Primary receipt of the project:
Are receiving primary for the project when completed all the work without flaws, which means the receipt of the preliminary work of all according to a contract of the project and after the end of the period prescribed for its implementation (the original term + additional period approved) can be received earlier if terminated contractor of the project before the end of the implementation period based on the speech addressed to the employer in this regard, according to the following procedures:
1 - The Contractor shall submit a letter to the point of her project made her feel when he finished all the work correctly and in accordance with the contract documents, and that the project is ready to deliver the first instance.
2 - The formation of a committee of receipt by the primary employer of its members is a Engineer, and identifies the date and the parking on the ground 0
3 - the contractor is notified of the date and the parking on the nature and based on:
A - Request the contractor.
B - Report of the Engineer in accordance with the inspection work prepared two weeks before the end of the decade.
4 - The Committee on receiving access to the documents and contract documents, namely, (the contract and conditions, including the specifications and bills of quantities and plans - change orders - minutes of meetings, test reports and performance - amendments - supply-ins - the minutes of the preview - any other documents important to the receipt of such observations that have been formulated during the implementation and how to avoid them).
5 - The Committee shall listed preview work on the nature and conduct the tests necessary to the process of receiving, as well as testing the functionality of the work of air conditioning and sanitary works, electrical and all that the Committee may deem necessary for the receipt of all actions such as checking water levels and dimensions of internal and external of the building and orientation longitudinal and transverse ... ... etc..
6 - The Committee will then fill out a form the primary record of receipt, and choose one of the following cases according to the settled opinion was based on sampling and testing conducted by the receipt of the project are:
A - that all work had been fully implemented in accordance with the plans and specifications, conditions and technical assets, and the Committee recommends that the receipt of the project Astelama appealable.
B - that all actions have been implemented in accordance with the plans and specifications and conditions with the exception of some simple observations on some of the work can be accepted by a technical with a resolution of an appropriate them, or with the presence of defects has not been implemented does not prevent the benefit from the project and do not affect the integrity of the project. Can be dispensed with and the value of not more than 20% of the total value of the contract, the Committee recommends that the receipt of the project is appealable to the discount compared to the observations and deficiencies of the final extract.
C - that all actions have been implemented in accordance with the plans and specifications and conditions with the exception of some of the work described in the note list (the list is the preparation of the observations) and attached to this record, which the contractor shall be completed within a period agreed upon. And that such acts do not preclude the use of the project in its current state, the Committee recommends that the receipt of the project with the contractor's commitment to end the list of notes within the specified period, and then the Committee shall stand again on the project and write a report on those notes.
D - that many of the businesses that have been implemented by many observations, or there is incomplete works of the project is not indispensable, and that the project in its current state can not be receiving the first instance to the large number of observations and deficiencies, and in this case is This record is a record of the display.
7 - is released the minutes of receiving primary (Form No. 13) and signed by all members of the Committee and given the contractor a copy of it, and notes that once a receipt primary and adoption of the employer, the contractor deemed to have fulfilled its obligations according to the contract, and he deserves to pay all dues except book them until the completion of the notes or resolved as a result of deficiencies and poor implementation 0
8 - If you can not for the receipt of an experiment of the air conditioning because of inadequate air temperature will be notified of all primary business project with a delay conditioning experiment until the appropriate time before the expiry of warranty period.
9 - The project may receive elementary deficiencies do not prevent the benefit from it if it is substantial and little value, if public interest so requires.
10 - left to the contractor after receiving primary responsibility for maintenance of the project and fix what appears during the first year warranty until the final acceptance of the project, and it will continue to be responsible for what may appear from latent defects for a period of ten years from the date of final acceptance.

Last Update
11/4/2011 9:45:05 PM