Steps to oversee the implementation of road projects - an earthworks 9

Modify the levels of manholes and septic tanks
Manholes:
1 - give permission to the contractor to remove the cover and frame each room.
2 - Verification of the reduction or increase is attributed in accordance with the plans and specifications.
3 - give permission to the contractor to re-install the frame and install a well and the work and the installation of filler cover
Orchards:
1 - give permission to the contractor break down and remove the waste and the transfer of any excavation work required and order him to comply with the requirements of security and safety, without causing any damage to persons or property.
2 - Verification of the modified level of the walls and ceiling and connecting buildings.
3 - After receipt of the roof lifted or lowered in accordance with the plans and specifications.
4 - check the levels of nutrition and drainage pipes and welds.
5 - to verify the cleanliness of the orchards of the waste after the termination of employment.
Septic tanks and manholes new:
1 - check the sites septic tanks and manholes in accordance with the plans.
2 - check the levels of drilling and measuring and clean as well as the necessary orientation.
3 - give permission to the contractor by pouring ordinary concrete.
4 - overseeing the casting process and then make sure the processing of concrete according to specifications.
5 - Supervise the work of the buildings of the groves in accordance with the plans and specifications.
6 - receive distress wood and armament of the groves in accordance with the plans and specifications.
7 - to give permission to the contractor poured the concrete for the groves.
8 - oversee the process of casting, and then make sure the processing of concrete according to specifications.
9 - check the levels of nutrition and sanitation.
10 - Supervise the construction of manholes and check the sizes and elevations.
11 - give permission to the contractor installing windows and installing manholes.
12 - give permission to the contractor Balrdm on septic tanks in accordance with the specifications.
13 - Verification of the cleaning and removal of waste from septic tanks.