Steps to oversee the implementation of electrical work for buildings 1

Grounding network of the building:
- Revision extensions of grounding connectors Almidat before pouring concrete.
- Measurement of the grounding conductor section and link metal parts of the building.
3 / 2 cans and lighting units in the ceilings:
- Checking the Boxes and lighting units installed and the way in place according to the charts.
- Revision Sizes dimensions of cans before placing reinforcing steel.
3 / 3 piping:
- Ensure good communication pipes containers.
- Match the pipe sections according to the charts and tables of the number of wires and wiring.
- - Make sure to extend the pipes, before casting her for all purposes (lighting - electric sockets - phone - bells - a computer).
3 / 4 of the sub-distribution boards:
- Matching panels supplied and installed on the approved samples.
- Make sure to install the panels in place with all the accuracy and the level of height above the ground.
3 / 5 keys and exits:
- Make sure the installation of light switches, boxes and cans of exits sockets in place and the level of height above the ground, according to the plans 0
- Install the pipe confirmation pack tight and good.
- Make sure the installation of light switches, boxes and cans of sockets and make sure their rise from the ground level.
3 / 6 wiring:
- Matching wire clips to various departments on the charts.
- Taking into account the lack of links within the pipes.
- Check wire colors and match the specifications.
- Check for cleats to connect the wires inside the cans out (Qassams) and do not connect the wires without the use of private terminals isolated.
- Checking the grounding wire Feeder with electrical circuits and matching-sections of the specifications and drawings.
- Review the distribution of circuits for different purposes and different way of linking Balqguata and quality connection.
- After wiring work is filler.

Last Update
11/5/2011 4:10:21 AM