The timetable for the implementation of the project:
Shall be in accordance with Article No. (13) of the Public Works contract, which states:
(The Contractor shall submit with his bid a timetable includes the order of the workflow, and the way proposed by the execution of the works, as well as the contractor to submit to the Engineer or the representative of the Engineer when requested to do so any detailed written information regarding the arrangements for the completion of the work and construction equipment, and temporary works which are to be contractor provided or used or created by circumstances.)
And procedural steps to be used as follows:
1 - the schedule is requested from the contractor immediately after receipt of the project site, and submit it within fifteen days of the request to be presented in a manner appropriate charts such as:
- How the charts (BAR - CHARTS) is often used in small to medium, and perhaps in some large projects such as roads, limited items.
- Method of critical path networks, and used in large projects.
And the contractor when making the schedule in one of the methods presented on two separate bodies, namely:
(A) The total of the table describes the periods of construction activity and as a whole and the sequence of activities, and this body made when signing the contract, and the decline initially to make sure Mntqath, and depends in principle with the observation that the approval does not relieve the contractor who submitted the consequences of what will be its errors.
(B) the detailed agenda and come subsequent to the adoption of the table the total first body (the total) and include a timetable partial detail of the stages of activity, and provide, within fifteen days of receipt of the site with a commitment to what has been approved in advance in the table total, and the aim of this body to the programming activity partially committed to the activities of the contractor to ensure that work in a systematic manner, and is based on the schedule and procedures of other considerations such as:
- Procedures for the submission drawings.
- Procedures for adoption of the articles.
- Purchase and supply of materials to the site, a measure for the contractor.
2 - and parking on site supervising engineer to conduct inspections, supervision and Alastelamat progress and success of the contractor in the completion of its work to a large extent on his ability to prepare a timetable reasonable and executive commitment. The response of the supervising engineer with the contractor to do business oversight on the scale used is essential to the workflow, and this is the program after the study and reviewed and approved by the Engineer and adopted by the employer binding on the contractor adhere to which the performance of the various business of the project.
3 - may also be required during the implementation of the business to make some amendments to the original program (whether due to the slow pace of the contractor in the execution or at the request of the employer) are in agreement between the engineer and the contractor, then ratified or approved by the employer, and shall be binding to the contractor.