Stages and the basic rules - the stage of preparation of Project 2

Delivering the Site:
The objective of this procedure the delivery location on the ground in the same place and the body that put the project is free of barriers to implementation, is done under the record signed by a technical committee formed for that purpose by the employer is made up of a representative of the employer and the supervisor and the involvement of the contractor or his delegate, in stand on the project site and make sure there are no barriers to prevent the start of implementation, progress and action is as follows:
1 - after signing the contract the employer shall notify the Contractor (by an official letter at the address set out the contract) specifying the date of delivery of the Site.
2 - The Committee shall stand on the project site and match the planned general location of the planned site for the project, and make sure there are no impediments to begin implementation. In this case, the liberation of the minutes of the delivery location on the form provided and shall be the date of the record is the date of the delivery site to the contractor and the beginning of the contract period.
3 - If there are impediments to the delivery site to the contractor are the preparation of the minutes stating that the obstacles, and after removing the Entrepreneur sets another date for delivery of the project site to the contractor.
4 - If you do not attend the contractor or his representative on the day fixed for the receipt of the site are the work of its usual procedure, and is released the minutes of delivery of the site as usual, be notified to the contractor by an official letter of what has been provided with copy of the record, is a history of standing committee on nature is the date of delivery site to the contractor and the beginning of the contract period.
5 - is the record of the origin and several pictures by the designated form (Form No. 1) and the receipt of the copy to the contractor.