Steps to oversee the implementation of a mechanical 3
|
Fire control system:
- All fire fighting equipment is approved according to the requirements of civil defense, according to the specifications of the project.
- Revision piping and how to install them.
- Make sure to install the equipment in accordance with the plans and manufacturer's instructions.
- Verification of the efficient operation of all parts of the network of fire.
- All the tubes are washed with water and the network immediately after the completion of the tests.
Tests:
- Test the water network system sprays water pressure not less than 15 atmospheric pressure for two hours or operating pressure for 48 hours.
- Test the network by releasing halon in fire-prone area.
- Test the network of carbon dioxide by releasing it on an area prone to fire.
|