Steps to oversee the implementation of a Roads Lighting 1

Coordination with the electric company:
- Coordination with the electricity company through a contractor of the project to locate electrical transformers that will feed the project, including the adoption of the minutes of the location of transformers.
Business combinations:
Receipt of the excavation:
- Are reviewed and the integrity of the dimensions of the excavations on the drawings and / or specifications.
Piping:
- Make sure pipes connect well with each other at the points of contact.
- Make sure the thickness of the layer of sand in accordance with the specifications and drawings.
- Check the status of the top layer of tape warning reclamation.
- Pour concrete around the pipes at road junctions as charts and / or specifications.
Grounding network:
- See section grounding connectors and ensure the continuity of the grounding conductors along the pipes.
- Make sure the installation of ground for each column, check the section of cable ground (in the case of a grounding network).
Places of columns:
- Review places the columns according to the charts.
Rules of the columns:
- Verify the integrity of the line of the rules along the street.
- Ensure the implementation of the dimensions of the rules according to the plans before authorizing the work pouring concrete.
- Make sure the concrete mix design.
- Make sure during the casting of the development of an installed base of the column according to the charts.
Manholes:
- Review the dimensions and location of manholes in accordance with the plans.
- Verification of the weight of manhole cover and thickness according to the specifications.
Installation of the columns:
- Audit vertical columns and openings should be borne in mind that the fuse box in one direction.
- Directing the contractor put Muscat handles the columns (single and double) perpendicular to the axis of the street.
Installation of the fuse boxes:
Make sure to install the fuse boxes in the column, well, check the parties to deliver and install the cables.
Extension cable:
- Checking the insulation of cables and check-sections according to the plans and specifications.
- Control of the individual cable and extend it in an artistic way, and avoid any kinks along the process by the individual.
- Taking into account leave the additional parts of the cable room inspection.
- Examination of the end of the cable connectors and the degree of isolation.
Installation of indexes:
- Make sure to install the detectors well and according to the manufacturer's instructions.