General Conditions3

Stop working:
Shall be in accordance with Article No. (32) of the Public Works contract, which states:
(The Contractor shall upon written order from the employer to stop the course of the work or any part thereof for a period or in a manner considered by the employer is necessary for the safety of work, and the contractor during the period of the suspension that the labor protection and to ensure that walking to the extent it deems necessary Engineer.
The employer shall bear the costs resulting from the suspension if they are in one of the following cases:
1 - If provided for in the contract.
- If necessary to do the work in a fundamentalist, or was due to weather conditions, or was due to failure of the contractor.
3 - If necessary for the safety of the work or any part thereof).
Extend the period of completion of the work:
Is to extend the duration of the contract according to Article 9 (b) of the insurance system, government procurement and implementation of projects, which states:
2 - an order issued by the administrative body to stop work for reasons beyond the contractor with the government there. And may not extend the duration of the contract is for the reasons referred to above only after consulting the Ministry of Finance and National Economy).
In all previous cases have to be a study timetable submitted by the contractor and approved; to determine the reasonable period of extension and recommend them to his authority.
Amendments, additions and cancellations:
Shall be in accordance with Article No. (43) of public works contract, which states:
Shall be in accordance with Article No. (43) of public works contract, which states:
(First, the engineer after obtaining the consent of the employer or the limits of the powers conferred upon him to make any change in the form or the type or quantity of work or any part thereof which it may deem appropriate, and the contractor implement it to not lead to a change in place of the contract or exceeded the limits set forth in the following paragraph:
Second, the employer may - during the execution of the contract - increase the amount of business by not more than ten percent (10%) of the total value of the contract, as he may decrease the amount of business by not more than twenty percent (20%) of the total contract value that is going on in this case modify the value of the contract by increasing or diminishing accordingly.
Third: The Contractor shall not be any change of the changes referred to without a written order issued by the Engineer).

Last Update
11/4/2011 7:15:24 PM