Steps to oversee the implementation of road projects - an earthworks 2

Reclamation:
1 - check the clean areas of construction (roads) of the waste and grass and trees and any other materials not needed by the build process.
2 - Verification of soil classification according to the specifications.
3 - in the case of disqualification of materials or in the case of insufficient output given permission for the drilling contractor to supply materials to bridge the valid from off-site according to the specifications (according to Form No. 6).
4 - an experiment on the Proctor backfill material suitable for determining the maximum dry density and optimum moisture content.
5 - Verification of the backfill in layers according to the specifications.
6 - does not allow adding a layer later only after confirmation of the previous class by conducting the necessary tests on them.
7 - Messahaa receipt of each layer.
8 - Check the rate of compaction and moisture content of field density testing and placement to the maximum dry density according to the experience of Proctor.