Receipt of rebar
|
A: rebar foundations:
1. Ensure the cleanliness of steel and no steel.
2. Review the type and rebar diameter, number and length.
3. The formation of iron and assemble according to the drawings.
4. Review places Ohaar iron columns and linked Bakanat.
5. Review diameters and the number and length of iron Ohaar columns.
6. Sure of a good iron shell.
7. Installation of the eyes as if to Ohaar columns.
8. Installation of iron chairs for the top.
B: rebar columns and walls:
1. Ensure the cleanliness of steel and no steel.
2. Review the type and rebar diameter, number and length.
3. Review the number of alkanes and installments and linked Baloseach.
4. Make sure the installation as if the eyes of the columns.
5. Ensure the cleanliness of the column before Altagafil.
A: Bishop of rebar reinforced concrete:
1. Ensure the cleanliness of steel and no steel.
2. Review the type and diameter and number of reinforcing steel bars.
3. Review links and lengths of reinforcing steel bars according to drawings.
4. Review the dimensions Kanat ceiling beams as well as the number of installments and at equal distances by graphics.
5. Quietly put down rebar slabs and between robustness and aspects of the beams.
6. To link rebar beams with the upper and lower alkanes wire bond linked well.
|