Steps to oversee the implementation of projects- buildings 5
|
Flatwork:
1 - Adoption of samples of materials to specifications.
2 - Check the conformity of supplied materials to the site in accordance with the approved samples.
3 - a comprehensive review of levels and adjust well.
4 - Review trends for flooring.
5 - Review the business health of the extensions of exchange, testing and closed end so as not to blockage.
6 - Review of electrical installations and especially of what is buried under the floors.
7 - Supervise the work of installation of flooring and receive jobs according to the plans and specifications.
Of the coatings (internal / external):
1 - Adoption of samples of materials to specifications.
2 - Verification of material supplied to the site in accordance with the approved samples.
3 - Verification of the flat surfaces.
4 - Supervise the work of installation and receipt of business in accordance with the plans and specifications.
|