Steps to oversee the implementation of road projects - an earthworks 8
|
Stone coatings:
1 - Check processing tendencies dust according to the plans.
2 - Adoption of precious samples.
3 - give permission to the contractor to supply stones and examined after delivery.
4 - supervising the installation of stone according to specifications.
5 - Ensure the work of construction joints.
Concrete coatings:
1 - Check processing tendencies dust according to the plans.
2 - mixing ratios of the adoption of concrete (regular or armed).
3 - give permission to the contractor poured the concrete (normal / armed).
4 - overseeing the pouring of concrete (normal / armed).
5 - Verification of the treatment works for the work according to specifications.
6 - make sure the work of construction joints.
|