Stages and the basic rules - Phase Executive 8

Procedure for the withdrawal of work:
1 - are the appropriate functional of the employer shall notify the Contractor in writing and by registered mail Bakhalalh its obligations and the need to correct the situation within fifteen days of the date, and that was during that period to respond in writing to disclose his responsiveness to remove the violation, and provide a timetable rate to remove them if necessary.
2 - In case of failure to respond to the contractor within fifteen days addressing the contractor CABLE Further to the letter of the previous reference to it, and given a period of fifteen days, the did not respond to you the relevant functional of the employer to the work of a full report on the project and actions taken about it and the reasons for withdrawal of the project.
3 - take the case to a screening committee offers its recommendations about the issue by bringing the art, and then displays it on the authority to issue the final decision.
4 - If approved by the authority to withdraw the project issued the administrative decision to withdraw the project, and shall notify the contractor officially, and provides some of the actors in the decision of withdrawal (such as the Ministry of Finance and National Economy - General Auditing Bureau - Department of Zakat and income - and the rating agency contractors, Ministry of Public Works and Housing - Ministry of Interior).
5 - After the signing of the withdrawal decision of the authority supervising the contractor to stop work Khttiyaoablagh need to surrender all the assets of the Active building materials and equipment, and the book other than the reservation Active substances that damage is feared.
6 - Based on a decision to withdraw the employer as soon as a committee to limit the work completed and remaining work and all the assets to site, the contractor shall be notified in writing of the date and the parking is taken on the project and signing the record.
7 - Contractor will be informed in writing of the withdrawal decision by registered letter or telegram including notification of the decision and the need to delegate presence in time to witness a few of the work carried out and the remaining works, materials and equipment and sign the minutes of the Committee.
8 - If you do not attend the contractor or his representative at the time being limited in his absence, and notify its result, and forfeits his right to object or reservations for the minutes recorded.
9 - not recorded in the record of the work done but what has already been approved on the supervision and in conformity with the specifications under the report of receipt of the work progress, and recorded all materials and equipment at the site exclusively description, type, quantity, and are not the owner obliged to take the materials and equipment location, but to the extent necessary to complete the work, and above that cost the contractor be transferred from the site.
10 - the point of supervision to limit quantities of unfinished business, and is set up tables for the full amount of the remaining actions to be implemented within the original contract, with the addition of agenda items that you need to remove or repair, and take into account when you make withdrawals as follows:
A - not the final release of the security (performance bond) and booked until the final accounting with him.
B - Complete the rest of the unfinished business at the expense of the contractor in accordance with the original system.

Last Update
11/4/2011 9:37:21 PM